Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).
2023-08-25
A.fast tracking
B.what-if scenario analysis
C.resource leveling
D.critical chain methoD.
参考答案:A
B.what-if scenario analysis
C.resource leveling
D.critical chain methoD.
参考答案:A
进度压缩技术包括赶工和快速跟进。(74)A.快速跟进 B.假设情景分析 C.资源平衡 D.关键链法