The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ).

2023-08-25

A.Cost Variance
B.Schedule Variance
C.EarneD.Value
D.Cost PerformeD.Index

参考答案:A

BCWP与ACWP之间的差值是 。

A.成本偏差 B.进度偏差 C.挣值 D. 成本绩效