Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .
2023-08-25
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources
参考答案:B
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources
参考答案:B
由于团队成员之间的冲突,造成了项目进度落后于计划,为了解决冲突以使得项目如期完成你应该考虑。A.重新安排时间表 B.执行资源调配C.进行反向资源分配调度D.利用关键的主要资源