In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law,a project with 10 stakeholders has ( ) potential communication channels.

2023-08-25

A.10
B.45
C.50
D.100

参考答案:B

在沟通过程的需求分析中,项目经理应该考虑项目沟通的复杂性,将潜在的沟通渠道或路径的数量作为一个指标来计算。根据麦特卡夫定律,一个项目有10个项目干系人的时候,将有(73)条潜在的沟通渠道。