A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) .

2023-08-25

A.assign change tasks to project members
B.call A.meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline


参考答案:D

项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。

选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。

由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。