If the approved change requests have an effect on the project scope,then the corresponding component documents and cost baselines,and( )of the project management plan are revised and reissued to reflect the approved changes.

2023-08-25

A.developing baselines
B.testing baselines
C.schedule base lines
D.ending baselines

参考答案:C

如果批准的变更请求对项目范围的影响,那么相应的组件文件和成本基线,和进度基线的项目管理计划。修订再版反映批准的变更。(75)A.发展基线 B.测试基线 C.进度基线 D.结束基线