Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.

2023-08-25

A.work breakdown structure
B.baseline
C.software requirements specification
D.plan


参考答案:A

翻译:在项目进度计划制定前,制定者应该有一份工作分解结构,一份针对每个任务的工作量估算,以及可用资源列表。A.工作分解结构 B.基线 C.软件需求说明书 D.计划