Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
2023-08-25
A.independent resource
B.individual work load
C.work milestone
D.work package
参考答案:D
B.individual work load
C.work milestone
D.work package
参考答案:D
WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。A. 独立资源 B. 个人工作负荷C. 工作里程碑 D. 工作包