The perform Integrated Change Contorl process is the uitimste responsbilityof the (请作答此空) ,Although changes my be intitated verbally,they should be recorded in writtern form and entered into the ( ) syste.

2023-08-25

A.resource manager
B.division manager
C.functional manager
D.projeet manager

参考答案:D

翻译:执行综合变更控制过程是(请作答此空)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入( )系统。A. 资源管理员B. 部门经理C. 职能经理D. 项目经理