The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

2023-08-25

A.Contingency reserve
B.Project profit
C.Management reserve
D.Special fund

参考答案:C

项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。