A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )

2023-08-25

A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

参考答案:D

项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。
选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。