All of followings should be done by the project manager during project control except ().

2023-08-25

A.Determine the a change has occurred
B.Ensure that a change is agreed
C.Make sure all changes are approveD.by management
D.Manage changes as they occur

参考答案:B

译文:项目经理不应该在项目控制过程中执行的工作是()。
A)确定变更已经发生
B)确保变更已达成共识
C)确保所有变更都获得管理层批准
D)在变更发生时,对变更进行管理

相关推荐