Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.
2023-08-25
A.cost management plan
B.risk management
C.scope management plan
D.management schedule
参考答案:D
B.risk management
C.scope management plan
D.management schedule
参考答案:D
翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划