The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。

2023-08-25

A.Chang control board变更控制委员会
B.Project management office项目管理办公室
C.Project manager项目经理
D.Configuration management officer配置管理员

参考答案:C