The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).
2023-09-01
A.periodic project reports,periodic visits to the customer,and telephonic exchanges
B.subordinates,project team members,and the project sponsor
C.one-time reports,weekly reports,and monthly reports
D.the telephone,facsimile,and data transmission
参考答案:A
B.subordinates,project team members,and the project sponsor
C.one-time reports,weekly reports,and monthly reports
D.the telephone,facsimile,and data transmission
参考答案:A
项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。