编制某分项工程预算定额人工工日消耗量时,已知基本用工,辅助用工、超运距用工分别为20工日、2工日、3工日,人工幅度差系数为10%,则该分项工程单位人工工日消耗量为( )工日。
2023-05-12
A.27.0
B.27.2
C.27.3
D.27.5
参考答案:D
B.27.2
C.27.3
D.27.5
参考答案:D
(20+2+3)×(1+10%)=27.5(工日)