1、A financial analyst determines the after-tax operating cash flow for a proposed project’s first year using the following estimates. 财务分析师使用以下估计确定拟议项目第一年的税后经营现金流Sales revenue 销售收入 $2,000,000Operating costs 运营成本$1,000,000Depreciation 折旧$200,000Income tax rate 所得税率35% The after-tax operating cash flow for this project in its first year is:( )第一年的税后经营现金流为( )

A、$520,000

B、$650,000

C、$720,000

D、$850,000



参考答案:$720,000