( ) must be between on-line deployment and final acceptance.
2023-08-25
A. Detailed design
B.Test run
C.Internal testing
D.Contract signing
参考答案:B
B.Test run
C.Internal testing
D.Contract signing
参考答案:B
翻译:
一定是处于上线部署和最终验收之间。
A.详细设计 B.试运行 C.内部测试 D. 合同的签订