( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.
2023-08-25
A.The control accounts
B.Funding requirement
C.The cost estimates
D.The cost baseline
参考答案:D
B.Funding requirement
C.The cost estimates
D.The cost baseline
参考答案:D