Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( )
2023-08-25
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call A.meeting of the change control board
D.change the project's objectives
参考答案:C
B.contact the customer to determine if the change adds value
C.call A.meeting of the change control board
D.change the project's objectives
参考答案:C
项目经理认为修改项目范围可以为客户提供增值服务。项目经理应该通知项目变更控制委员会召开会议。