During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate.This duration is what you commit to complete the project.What is wrong with the scenario?

2023-09-01

A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate should be the same as the customer's required completion date

参考答案:B

解析:当你打算坐下来评估每个任务所需的时间和总共的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是( )?
团队使用这种方法并没有产生太长时间的估计和估计故事。
团队不需要创建估算,不需要用到网络图。
估计太长了,应该由管理人员来制定。
项目估算应与客户要求的完工日期相同。